Skip to main content
Track Fixed contract sizing
2 / 7
Library

1994issue C041-10

Starting capital from worst-case portfolio walk-forwards

The historical workflow set a 2 percent per-trade cap and a 35 percent overall-capital cap first, then replaced a single-date capital figure with a walk-forward distribution of required starting capital.

  • A 2 percent per-trade cap and a 35 percent overall-capital cap were set as simultaneous exposure bounds before any start-date capital study.
  • A single January 1 1981 start produced a 5459 capital-required figure that the same study later treated as an optimistic artifact of a favorable start date.
  • Consecutive daily starts through 1990 produced an average capital requirement of 10576 and a standard deviation of 2049, which pushed a conservative start band to at least 17000 to 19000.
  • The same 2 percent per-position rule on a 25000 account forced many signals to be skipped because initial risk exceeded 500.
Entries in this reading3 entries

Exposure bounds came first

A 2 percent per-trade cap and a 35 percent overall-capital cap were specified as simultaneous exposure bounds before any start-date capital study.

Editorial note: TradersWeek maps that setup onto Fixed contract sizing, Risk of ruin, and Drawdown limit. Those filters keep a loss or exposure decision bounded before a trade is placed and throughout the position. The archive describes the caps and the later capital study without assigning those method names.

A loss streak was not treated as proof

Multiplying one observed streak of 13 losses by an average loss of 1455 plus a 3000 margin buffer produced a 21915 starting-capital estimate that the text rejects as under-supported.

One start date was later treated as favorable

A single January 1 1981 start produced a 5459 capital-required figure that the same study later treated as an optimistic artifact of a favorable start date.

Repeating the portfolio simulation from consecutive daily starts through 1990 produced an average capital requirement of 10576 with a standard deviation of 2049.

Starting capital from one date versus walk-forward starts

A single January 1981 start made the book look cheap at $5,459. Across walk-forward start dates the same rules needed $10,576 on average and $14,105 in the worst case, so the one-date figure is the easy outcome, not the funding rule. Those three amounts are the figures the article states from the original simulation and from the worst-case study table.
A single January 1981 start made the book look cheap at $5,459. Across walk-forward start dates the same rules needed $10,576 on average and $14,105 in the worst case, so the one-date figure is the easy outcome, not the funding rule. Those three amounts are the figures the article states from the original simulation and from the worst-case study table.Six-futures portfolio (British pound, cotton, Deutschemark, yen, orange juice, Swiss franc) · Walk-forward start dates, 1981–1990 · 1981-01-01T00:00:00.000Z to 1990-12-31T00:00:00.000Z

Walk-forward starts after the end of 1990 were dropped because they covered less than a year. Each run used a 2 percent per-trade cap, a 35 percent overall-capital cap, six-tick slippage and a $50 commission.

A small shortfall chance was still rejected

Under a normality assumption, 14105 of starting capital left about a 4 percent chance of still being underfunded, which the text called unacceptable.

Planning for a three- or four-standard-deviation shortfall, rather than the 1.75-sigma 14105 level, raised the conservative start band to at least 17000 to 19000.

Editorial note: TradersWeek reads the refusal to accept that remaining underfunded chance as a Risk of ruin filter, and the higher start band as a Drawdown limit on opening capital. The archive reports the figures without those labels.

The same cap skipped signals

The same 2 percent per-position rule on a 25000 account forced many signals to be skipped because initial risk exceeded 500.

Editorial note: TradersWeek reads that skip rule as Fixed contract sizing applied before entry.

Educational research material, not investment advice. Historical source context does not establish present-day performance.
2 of 7 in the Fixed contract sizing track
19941-6 pp.Next on Fixed contract sizingBound small-account risk before adding leverageCap the cash lost on one fill first, so a short run of bounded losses cannot shrink equity until the next trade cannot be placed.
All readings on this track · 7 readings
  1. 1987Volatility-layered mechanical system with fixed contracts
  2. 1994Starting capital from worst-case portfolio walk-forwards
  3. 1994Bound small-account risk before adding leverage
  4. 1996Variable position size after entry
  5. 1996Equity path filters for contract size and drawdown
  6. 1997Stop distance, equity caps, and trading halts
  7. 1999Size-matched buy-and-hold evaluation for stock systems
All 7 readings tagged Fixed contract sizing
Also on Fixed contract sizing5 readings